The scope of this project includes the complete upgrade of the Distributed Control System (DCS), Boiler Protection System (BPS), Turbine Control System (TCS), Turbine Protection System (TPS), Turbine Supervisory Instrument (TSI) and conversion to high-pressure Turbine Hydraulic Governor Oil System at Kapar Energy Venture's Unit 3 Power Plant.
Client: Sabah Electricity Sdn Bhd
Completion Date: March 2016
We successfully completed the project in July 2016, four (4) months after its commencement in March 2016. The project involves the upgrading of DCS for CCP Boiler, Steam Turbine and GT Interface using latest control system from Valmet DNA DCS System at Patau-Patau Power Plant owned by Sabah Electricity Sdn. Bhd.